Energy Pod – 560kW Wales

560kW Heating Solution

A Shaw Renewables Energy Pod was the answer to our client’s storage issues and the key to unlocking their existing biogas plants full potential. 

The Ceredigion based animal feed producer was having humidity issues in their warehouse, so needed a large heating solution. After talking with the customer it was discovered that their existing biogas plant had the capacity to produce an extra 120m3/hr of biogas if they increased their feedstock. Our engineers sized, designed and fabricated a containerised biogas boiler system that would utilise the additional biogas whilst generating a sufficient amount of heat to combat their humidity problem.

The plant room was fabricated in our workshop over 3 weeks and delivered to site ready to be connected to the clients biogas plant controls. The 20ft container houses all of the plant equipment.

RHI BIOGAS BOILERS RENEWABLE HEAT INCENTIVE

The customer is part of the Renewable Heat Incentive Scheme (RHI), benefiting from payments for 20 years.

You can find out more about the Government’s RHI scheme on the Ofgem website.

 

Shaw Renewables Biogas Boiler

Sector:          Food Production

Location:      Ceredigion

Fuel:              Biogas 

FUEL CONSUMPTION:

120m3/hr Biogas

SERVICES PROVIDED:

  •  Design of RHI compliant system
  •  Installation and commission of a containerised 599kW biogas boiler
  •  Connection of system
  •  Installation of Pipework

PLANT ROOM:

A containerised plant room now houses:

  • 1no. 599kW Viessmann Vitoplex Boilers 
  • Dunphy Burner
  • Ancillary control
  • Pressure equipment
  • Metering equipment which meets Ofgem’s requirements

HEAT USAGE:

Space and process heating:

  • Warehouse